Multiple Projects at PMIInsight

Ignoring resource constraints, this Master Schedule had a makespan of 264 days. Using Microsoft Project’s Resource Levelling function, a makespan of 506 days was achieved. This same Master Schedule optimized using ORITAMES produced a makespan of 396 days!